SR-101 Intelligent Transportation Systems (ITS) Infrastructure


Reyez Construction Projects

SR-101 Intelligent Transportation Systems (ITS) Infrastructure




Reyez Construction Projects

SR-101 Intelligent Transportation
Systems (ITS) Infrastructure

Location:

Southwest

Client:

Arizona Department of Transportation

Construction Value:

$15,038,065

Delivery Method:

Design Build 2 Step

Year Completed:

2023

Specialties:

Infrastructure & Site Development

Location:

Southwest

Client:

Arizona Department of Transportation

Construction Value:

$15,038,065

Delivery Method:

Design Build 2 Step

Year Completed:

2023

Specialties:

Infrastructure & Site Development

Features & Highlights


Micro-trenching for safer, uniform and more environmentally friendly process


Utilization of five different conduit installation methods: Plowing, microtrenching, standard trenching, directional drilling and structure crossing carrier conduit.


Installation of over 370 pull boxes for owner and customer access.


Project Overview

The Arizona Commerce Authority (ACA) and Arizona Department of Transportation (ADOT) are working to expand access through the Arizona Statewide Broadband Strategic Plan. Reyez Construction and joint-venture partner CS Construction, Reyez Construction/CS, are building out the southern portion of the state’s new Middle-Mile Network, adding connectivity along Interstate 19 from Tucson to Nogales. This network brings high-speed internet connection to low-income, rural and tribal communities in Arizona who don’t have broadband access. In addition, the project added the necessary infrastructure ADOT needs to have in place for its Intelligent Transportation Systems (ITS).


Along 63 miles of interstate shoulder, the design-build team installed fiber-optic and high-speed internet infrastructure via broadband cable. The $15 million project includes trenching and installation of three-inch HDPE conduit with seven micro ducts, 288-strand fiber optic cable, triple pull boxes every 3,000 feet, and two new node buildings.


Micro-trenching, used for nearly one-third of this project, is a safer, less disruptive, and more environmentally sensitive process for installing broadband cable. It involves cutting a 4-inch-wide by 14-inch-deep trench, placing the multiduct, staking it down to avoid deflections, and then backfilling with cement slurry.


Features & Highlights


Micro-trenching for safer, uniform and more environmentally friendly process


Utilization of five different conduit installation methods: Plowing, microtrenching, standard trenching, directional drilling and structure crossing carrier conduit.


Installation of over 370 pull boxes for owner and customer access.